Project Name: Hanks pond spillway
Construction: 2019
Design Engineer: GZA Environmental
Contractor: Ron John Construction
Location: Hanks Pond- Watershed
Project Summary: Due to dam safety requirements, the spillway at Hanks pond was lowered and reconstructed. Water from Cedar Pond goes to Clinton Reservoir. This is a small Hazard spillway. The pond was lowered for doing the construction.