Chemical Line Replacement

Project Name: Chemical Line Replacement PWTP - Pretreat

Construction: 2019-2020

Design Engineer: Mott Macdonald

Contractor: Underground Utilities

Location: Pequannock Water Treatment Plant- Pre Treatment

Cost: $750,000.00

Project Summary: The city has installed a new chlorine generation system at Pretreatment facility. The pipes were installed to transfer chlorine from Pretreatment to the treatment plant. Four 6” pipe lines were installed to the system during this project.