North Ward Salt Storage Facility
Project Name: North Ward Salt Storage Facility
Construction: November 2022 to October 2023
Design Engineer: Grant Engineering & Construction Group, LLC
Contractor: Bismark Construction Corp.
Location: 51-61 Verona Avenue
Cost: $200,000.00
Project Summary: This project consists of the construction of a salt storage facility in the North Ward. The parking will consist of four equivalent parking spaces. The salt storage is a 45'x 50'x 35'-9 height structure with a capacity of 1,112 Cubic Yards and a site office structure.